For our Montpelier project, we installed a 300mm waveform cable across the road to the site boundary, reducing it down to 95mm to supply plots 1 and 2. Additionally, a 95mm run was installed on-site, extending towards plots 3 and 4. All properties were provided with 3-phase services due to their size.
The project was for the construction of four luxury homes in W5, London, with a value of £9.6m. One of the key challenges was the lack of available parking bays. Despite placing no-parking cones, they were frequently moved, and vehicles continued to park, making the installation process more difficult.
SSEN completed the Point of Connection (POC) to energise the supply, while UKPD served as the adopting Independent Distribution Network Operator (IDNO).