Case Study: Faith Community Church
February 20, 2025
Services: Gas & Electric
Client: Faith Community Church
Location: Bedford
This project involves installing a 63mm PE LP service from the network main located on the opposite side of the carriageway, terminating in a GC2 meter box.
Additionally, 50mm electric ducting, including a 35mm cable, will be installed across the carriageway.
The carriageway excavation will be completed in two halves under two-way traffic light control to ensure safety and minimise disruption to residents.