The Ashley Road project is a 4-6 month undertaking to install 2.7km of UKPN-spec cable ducting and high-voltage (HV) cable to support a new development by Haringey Council.
Phase 1 involves installing approximately 300 meters of ducting and cable from the northern boundary to the project site. This work will begin in residential areas, with careful planning to minimise disruption to residents. As each section is completed, the site will be restored to allow residents to reclaim parking spaces as soon as possible.
Phase 2 shifts to the southern part of the site to install the remaining 2.4km of cable along more complex sections of the TfL road network, including Monument Way and the A10 High Road. This phase presents additional challenges due to the high-traffic nature of these routes.